PROJECT DESCRIPTION

RAEC 07/2014 :

Construction of 33kV feeder (underground cable) from Al Nahdah 33/11 kV primary Substation to the proposed Dawah primary substation wilayat Masirah-Al Sharqiyah Governorate.

The project location was at Masirah and the client was Rural Areas Electricity company SAOC

The works primarily involved :

  • construction of 33/11kV primary substation
  • installation of 2x3MVA 33/11kV transformers
  • laying of 18KM 3C x 300sq.mm
  • Laying of 24F FOC cable.